Carrier John F. Kennedy Passes Preliminary Acceptance at Newport News
The US Navy has taken preliminary acceptance of the future USS John F. Kennedy (CVN 79) from HII's Newport News Shipbuilding. Formal acceptance of the second Ford-class carrier is due by March 2027.
The second Gerald R. Ford-class carrier has cleared preliminary acceptance at HII’s Newport News Shipbuilding, leaving the future USS John F. Kennedy (CVN 79) one formal step from delivery to the US Navy.
The Navy said the ship is “approximately 99 percent complete.” Preliminary acceptance lets the crew take the carrier to sea for testing and training before the service formally accepts it, which is planned by March 2027.
The Last Systems Aboard
The milestone comes after the carrier finished builder’s sea trials and acceptance trials earlier this year. The yard is now working through the final ship systems tests.
The Advanced Weapons Elevators remain the main item. The ship has 11 of them. Seven were turned over in August, and the remaining four are still in testing.
Capt. Mark Johnson, the Navy’s program manager for Ford-class new construction, said preliminary acceptance “marks a new phase for the ship and her crew, allowing them to get more water under the keel as they test and train underway.”
A Schedule That Moved Twice
Construction began in 2011. Delivery was first planned for June 2024, then pushed to July 2025, and then to March 2027. The delays were tied to the work needed to finish new systems on the ship, including the advanced arresting gear and the weapons elevators.
The March 2027 date is now the target for formal acceptance, after the at-sea period that preliminary acceptance opens up.
The Ship
CVN 79 is about 1,106 feet (337 meters) long, with a full load displacement of 100,000 long tons. It has room for more than 75 aircraft, putting it among the largest warships built.
Once delivered, the Navy expects the Kennedy to serve for roughly 50 years. It will take on global power projection and defense missions similar to those of the lead ship, USS Gerald R. Ford (CVN 78).
For Newport News, the handover would close out the second hull of the class, after a build that has run 15 years from the start of construction to preliminary acceptance.